CCAM's list of known problems and/or unsatisfied requirements at 400 Farmington Ave:

Priorities

  • Priority 1 - Critical
  • Priority 2 - Important and urgent
  • Priority 3 - Important, but not urgent

Table - List of Issues

Room Fixed? Priority Short Description Kevin Comments Goody Clancy Comments CCAM Comments
1389 DONE 1 No power Partially completed. To be completed week of 8/9 Electrician advises all outlets now installed Datacentrer office outlets not working
cell culture rooms No 1 CO2 supply      
cell culture rooms DONE 1 gas in all biosafety cabinets Inform Kevin Norton of which rooms are to be turned on. Gas system purge is complete. Advise Greg Nichols of which rooms require gas to be turned on.  
Autoclaves No 1 Need to get them up Tuttnauer is scheduled to install compressors on 8/9. Anticipated to be completed and units ready for use on 8/10. R1157 and R1716 are running. R1564 still pending additional piping  
Glass washers DONE 1 need to get them up   FIP advises glasswasher 1565 is running, and temporary racks have been provided. Please advise if there are any issues with operation of the equipment  
1388 DONE 1 need circuits in 2nd UPS/PDU     wire several 208V and 3-phase circuits to racks
MDF No 1 enable 10 Gb connection  

Is this an issue of missing physical infrastructure, or of network setup?

Issue is network setup

MDF to DC fiber connections need to work before the translational genomics and microscopy facilities become operational next week
1558 DONE 1 (2) L6-30R needed     for lasers
1558 DONE 1 5-15R duplex needed     on instrument rack
1558 DONE 1 hi-press air needed Contractor working on it High pressure air installed  
1545 DONE 1 hi-press air   FIP advises HP air was completed into this space. for air table (FIP is working on it)
1546 DONE 1 hi-press air neede   FIP advises HP air was completed into this space. for air table (FIP is working on it)
1547 DONE 1 need monkey bars     in hoods
1547 No 1 No power to receptacles in vaccum pump cabinet under the 2 hoods Notified electrican. electrician to investigate   Duplex Receptacles are there, but dead.
1547 DONE 1 chemical storage venting waiting for vent kit to arrive from mfgr. FIP advises vent kit was installed under hood
1547 No 1 (2) water taps and (1) cup sink Need to follow up with contractor on proposal status   in hood
1547 No 1 Add 2 duplex electrical outlets to each hood Reviewed with electrican to see what is involved to install. Need to coordinate with lab casewrok vendor and electrican   One duplex on each side of the hood is inadequate for an 8 foot hood
1547 No 1 Add at least 1 water tap to each bench Need to follow up with contractor on proposal status   a single tap on each bench is inadequate for a chemistry lab
1547 DONE 1 Install piping to permit vaccuum pump connect to hood Need to review with lab casewrok installer for hose route FIP advises Gibson provided routing and installed cutout. Noise-muffled Vaccum pump trays are provided under the hoods, but there is no way to feed a hose to the hood interior.
1547 DONE 1 data ports blocked     no cable coming from dataports hidden behind some of the writeup stations
1541 DONE 1 No elecrical service to receptacles along benchtop      
1542 DONE 1 No elecrical service to receptacles along benchtop      
1545 DONE 1 Circuits not added yet   Electrician advises all circuits added. User review needed once all lasers are installed - any excess circuits, including convenience circuits, should be cut back as the R1530 panels have been filled mostly from this room. Wall strip and overhead units are labelled with the desired number of circuits for 1545 and 1546.
1545 DONE 1 Holes need to be cut for electrical connections to outlets and table   Rings appeard to be installed. Please cut holes and install rings for our overhead units as done for Dr. Yu in 1558. 2 per overhead unit.
1546 No 1 A/C unit needs to be checked     A/C unit is above lasers, drain needs to be checked to ensure it won't leak.
1545 No 1 Missing elbow bracket for unistrut tank wall mnt     Need 3 more 90 degree brackets for tank strap-to-unistrut wall mount plus the spring nut, tanks are here already.
1574 No 2 extend curtain   Pricing request issued to FIP. Pending response extend blackout curtain to separate R1574 from R1573
1389 DONE 2 No AC Need to follow up with contractor FCU has been brough on line. Datacenter office cooling does not work
1271 No 2 install distilled water tap for MilliQ Temp. install complete. Perm. install of tap being scheduled by contractor   tap requipred for permanent installation of MilliQ water purification unit
1114 No 2 install distilled water tap for MilliQ Temp. install complete. Perm. install of tap being scheduled by contractor   tap requipred for permanent installation of MilliQ water purification unit
Varies No 2 Service carrier shelves   CCAM identified that shelves are too high at some service carriers. List was emailed to GCA, proposal issued to contractor, pricing is being submitted. List of rooms (incomplete): 1542,1545,1546,1556,1557,1558
1388 No 2 3rd UPS/PDU Elect. contracto scheduled to work on and complete week of 8/9. Install is complete. 125A breaker will be replaced with 150 when it arrives. wire UPS to PDU, wire PDU to bldg, startup & test, wire circuits to racks
1388 No 2 BMS programming Working with JCI Controls   select AC monitoring events need to be forwarded to CCAM pager and to several email accounts
1632-35 No 2 blocked outlets Punch list item   need to relocate wall outlets to match desk opening
corridor No 2 HVAC broken in NE corridor reviewing issue with architect and contracor Contractor is working on fixes. malfunctioning HVAC on about half the corridor and a few adjacent rooms all the way to break lounge - moisture, dripping condensation, high temperatures, etc.
1660 DONE 2 need shelves shelves located to room. need to be installed FIP advises shelves were installed. wall shelves missing
1547 No 2 Argon and Nitrogen lines to both hoods Temp. tanks installed. Need to review   running to both hoods from single N2 and Ar gas tanks
1547 No 2 Replace top drawers in cabinets with pairs of half-height drawers Need to follow up with lab casewrok installer to confirm drawers can be changed. Mfgr. staed the entire cabinet needs to be replaced   Required for small implements like spatulas, pipets. etc.
1545/46 No 2 Floor not level   Existing concrete floors were not level in some locations. This is an inherent condition of a renovated building. Had to shim up air table leg with extra tiles to compensate for uneven floor.
1540 No 2 Replace 2 wash sinks with regular cabinetry and benchtops and add overhead shelving Need to review scope with contractor and architect   Proposal was issued to GC The room currently has 3 wash sinks - only need 1.
1540 No 2 Place cup sink and 2 water taps on each bench top Need to review scope with contractor and architect Proposal was issued to GC Currently there is no water on the benches except for the wash sinks, 2 of which are to be removed.
1633 DONE 2 2 of 4 ceiling lights are out Punch list item Bulbs were replaced  
1633 No 2 HVAC balance   contractor was notified and will investigate No airflow seems to be coming from the supply diffusers in this room.
1547 DONE 2 No natural gas   Gas system has been purged. Contact Greg Nichols to have gas valves turned on for specific lab areas. No natural gas
1512 DONE 2 Add shelf or cabinet Need to review with user UV/Vis spectrophotometer will be moved to other room with shelves No shelf or cabinet to store UV/Vis accessaries
1365 DONE 3 Missing guest chair     The chair was found
1522 DONE 3 laser curtain track Informed contractor FIP advises installer has adjusted track.

curtain gets "stuck" at joint, can't fully open to either side

1565 No 3 shelf and outlet for milliQ unit Need to review with contractor   install appropriate components for installation of MilliQ water purification unit
1523 DONE 3 electrical stops not glass enclosed Punch list item FIP advises stops were replaced need to replace emergency electrical cutoff with glass enclosed version
1155 No 3 electrical stops not glass enclosed Punch list item Please verify the room number - 1155 is the GDB autoclave service room. Electricians have been replacing glass stops need to replace emergency electrical cutoff with glass enclosed version
1540 DONE 3 install duplex receptacle for oven and freezer Need to review location with lab staff   currently have to use extension cord to benchtop receptacle
Varies No 3 Shades at lab windows Dept. to provide room number for locations CCAM noted some labs have glare through the windows to the halls but do not have shades installed. Please identify a list of affected labs  
1388 No 3 adjust motion sensor Punch list item   cannot turn on lights when coming in from R1389
1558 No 3 Storage cabniet unfinished. Needs shelves/doors. Need to review with lab staff    
1555 No 3 Ethernet ports blocked by panel, has cable connected by not active. Need to review with lab staff Ports apparently activated, but jumper cables needed (by owner) Need at least figure out the port number so that the network people can diagnose on it.
1556 No 3 Storage cabniet unfinished. Needs shelves/doors. Need to review with lab staff    
1555 No 3 furniture spares     Spare parts for furniture are stored behind the island bench
1578 No 3 Door to 1579   Needs pricing and approval from UCHC, proposal is already out to GC for pricing Required to allow Wolgemuth acces to microscope room.
1608 No 3 Furniture Sofa is scheduled to be delivered 8/2. Task chair 8/11. Need to review poer strip routing and accessability Furniture delivered Kevin is obtaining wire management material for the power strips. deliver sofa and chair and install power strips under hutch
1608 DONE 3 3' white board Need to verify if 3' white bord is availble in attic stock FIP advises this was installed. install behind door
1511 No 3 Shelving and tack boards need to be installed Punch list item   Please see yellow notes on wall in R1511 for correct places. If there is a problem with the locations please call ext. 4686.
hallway DONE 3 tack board needed Currently being fabricated Tack boards were installed tack boards on wall of main lobby (poster area) not installed
various No 3 broken shades Punch list item   broken shades and/or with missing parts and not installed at several windows throughout the building
1630 DONE 3 whiteboard missing Punch list item. Need to follow up with contractor FIP advises whiteboard was installed  
1630-35 No 3 marker shelves needed Need to review with users Carrie is pursuing options with BKM small sections of markerboard shelves needed next to the write-on windows
1636 DONE 3 privacy glass occupant is no longer is requiring film   door glass needs film covering or replacing with privacy glass
various DONE 3 lights don't turn off   Electricians advise they have adjusted all rooms - please note any rooms with remaining issues by number. Please also note that in some rooms the sensitivity has had to be turned down somewhat to prevent equipment or air system noise from tripping the sensors. sensors need to be adjusted in almost every lab and office - almost every room remains lit at night in a totally empty building
1501 No 3 filing cabinet bars needed notified BKM. Need to follow up GCA reviewed with BKM - BKM advises bars were supposed to have shipped with the cabinet and will follow up. check with Karen x1452
1603 No 3 more shelving needed Need to review with occupant   check with Charles x1655
1545 DONE 3 missing one fluorescent bulb Punch list item  

1550 No 3 Additional lighting above benches     Visibility is poor above lab benches. Kevin Norton contacted and requested it be put on wiki list. Contact is Dr. Irina Semenova (Rodionov Lab)
1571/1572 No 3 Laser curtain rehung   Valance of laser curtain has fallen down, velcro trip not adhering to track. See Dr. Yi Wu Rm #1607